SUBCONTRACTING IN NAVISION

Types of Subcontracting procedure in the Microsoft Dynamics Navision

Microsoft Dynamics NAV having mainly 2 types of Subcontracting Orders handling


  • Subcontracting Order given to the out side company

In this type of Subcontracting we are giving partial or full material to Outside company and that company doing some work for us and finally sending the product to us. This is the most important type of Subcontracting. This procedure is as follows.

a) Create a Subcontractor Location

Create a Subcontracting Location from the Location Card

Warehouse->Setup->Locations.

Fill the details as per normal Location creation procedure only difference is that you have to go to the Tax Information Tab there you select the Subcontracting Location as shown in the picture.


b) Create a Vendor Card

Create the Subcontractor as vendor as normal procedure. After that you have to attach the vendor to Subcontracting Location from the Tax information Tab in the Vendor card. Where you have to select subcontractor, Subcontracting Location that we created just now and Commisioners Permission details. For more information see the the picture.

c) Create Work Center

This is the one of the most important area where specifiying the work center area. Better you create one work center for one Subcontractor. For that go to the Workcenter Card from

Manufacturing --> Capacities-> Work Centers.

In that press F3 to create a new work center and enter the information based upon your need only difference is that in the Posting Tab you have to select the Subcontractor No.

d) Create a BOM

Create Production BOM for the subcontractor from Manufacturing -> Production Design -> Production BOM. Where you specify the materials that given outside for jobwork/Subcontracting Work.

e) Create a Routing

Create a Routing from Manufacturing->Capacities->Routing.
Where you specify the Work Center No. as subcontracting work center just now we created.
Attch the BOM and routing no to the Item Crad, ie, in the Replenishment Tab

f) Create a Released Production Order

Create a Released Production oder from Manufacturing->Execution->Released Production Orders or MRP.

g) Run Subcontracting Work Sheet

Open the Subcontracting Work Sheet from Purchase->Order Processing-> Subcontracting Work Sheet,
After that click Functions(Button)-> Calculate Subcontracts, in that window you have to specify the work center number in the Work Center Tab and Production Order in the production Order Routing Line Tab after that press Ok, to calculate the number of subcontracting lines.
Then the Subcontractor Lines will appear in the Subcontracting Work Sheet then you have to click Functions(Button)-> Carry Out Action Message. After that the Subcontracting Order will be created.



h) Material Issue Or Sending Material to Subcontractor

Open Subcontracting Order from Purchase->Order Processing-> Subcontracting Order
You have to click Line->Order SubCon. Details
Go to the Delivery Details Tab , enter
Delivery component for -: as number components material you are sending
Then click Function->Update Issue Details then automatically update the material to be issued. After that click Send(Button) to send the material, then system automatically create the DC for the material.

i) Receiving Materials Or Receiving Material from Subcontractor

For Receiving materials again got to the Line->Order SubCon. Details From Subcontracting Order. In that enter the Vendor Shipment No. & Posting Date. Then go to the Receipt Details tab, there enter Qty To Accept, Qty To Reject etc like information.
Finally click Function-> Update Receipt Deatails to update the consumption qty lines also. Then click the Receive Button to receiving material. You can take the print of the GRN form the noramal way.


  • Other company given Subcontracting to Us
In this case Subcontractor giving partial or full Raw materials free of cost to us and we process some task based upon that and produce some product. Finally we sell that product to the Subcontractor with less Consignment Material.Consignment Material is that material given by the Subcontractor free of cost.

The process is as follows


  1. Create a Vendor Card for Subcontractor
  2. Create Non-Stock Item as Materials Supplied by the Subcontractor.
  3. Inward the material using Purchase Order and Warehouse Receipt.
  4. Produce the product by normal procedure.
  5. In the sales order you have to specify one more extra line as G/L account consignment as -ve entry.
  6. Better you have to design a separate Report for consignment Sales Invoice.
[disqus][facebook][blogger]

Jubel Thomas

{picture#https://plus.google.com/u/0/photos/116645982191572612106/albums/profile/5718535508567382818} Having 9+ years of Dynamics NAV Experience with Modules like Finance, Sales, Manufacturing, Warehouse, Purchase, Human Resource etc. Also know LS retail, Dynamics AX, Business Intelligence. {facebook#https://www.facebook.com/Navision-Planet-347570178709579/} {twitter#https://twitter.com/NavisionPlanet}

Contact Form

Name

Email *

Message *

Powered by Blogger.